NOTICE TO RESIDENTS

Infrastructure Construction Stage 2 – Jack’s Point Village – Upcoming Work

03 April 2019

Darby Partners wishes to advise the Jack’s Point Residents and Owners Association and all other interested parties that it is making changes to the construction areas in April, to allow for the construction works for Stage 2 of Jack’s Point Village to continue.

The construction areas will be securely fenced off1, with all disruptions (including noise and dust) to be closely monitored. The expectation is that noise pollution will be minimal; potential dust issues will be managed by regular wetting down by water trucks as necessary.

construction-03-April-2019.jpeg

You will notice the existing fence lines to the north of Lake Tewa will be extended to allow for earthworks between Lake Tewa and the Golf Course to be completed. During this time the Lake Tewa loop track will be closed (access to the Golf Course from the northern part of Lake Tewa) however you will still have access to Lake Tewa up to this northern point of the lake.

Further to this, new fencing will be installed on the southern side of Clubhouse Road along with temporary traffic management. This is to allow site areas to be secure for construction and to provide a safe crossing of Clubhouse Road for both public and construction vehicles.

The Stage 2 works are expected to take approximately 12 months, depending on weather conditions.

For any queries, more information and to receive further updates on the Village, register at our website www.jackspoint-village.com.


NOTICE TO RESIDENTS

Infrastructure Construction Stage 2 to Commence for Jack’s Point Village

13 August 2018

Darby Partners wishes to advise the Jack’s Point Residents and Owners Association and all other interested parties that it is to commence the construction of Stage 2 works of the Jacks Point Village in late August 2018.

Stage 2 works will be established shortly, with earthworks likely to commence before the end of August. The Stage 2 works are expected to take between 12-16 months, depending on weather conditions over the duration of the project. 

Jack's Point Village construction area fencing plan

The construction area will be securely fenced off (see construction area fencing plan), with all disruptions (including noise and dust) closely monitored. Note that access to the trails and Lake Tewa will be maintained however there will be some re-routing of these with the Stage 2 site. The expectation is that noise pollution will be minimal; potential dust issues will be managed by regular wetting down by water trucks as necessary. 

This work lays the foundations to support future development within the Village which will in due course benefit all residents. 

For any queries, more information and to receive further updates on the Village, subscribe to news updates or register interest with the sales team.

 

Photo Essay

As the story of Jack's Point evolves with the new Village, renowned New Zealand photographer Camilla Rutherford has been capturing the landscape with each season.

Follow the story here



Media Enquiries

For all press and media enquiries relating to Jack’s Point Village, please contact: 
Nicole Haysom
Email: nicole@peadpr.co.nz 
Tel: 021 903 117
Outside NZ: +64 21 903 117

Other media resources: